Tag Archives: Elgan Roberts

Climate change mitigation and getting off oil. Latest installment!

Thursday was a good day. we were invited by the Climate Change Environment and Rural Affairs Committee in Welsh government to show our plans, discussions and projects and so on Wednesday we had an NT and partners day. The weather … Continue reading

Posted in Biomass, Hydro, Wales | Tagged , , , , , , , , , , , , , , , , , | Leave a comment

Penrhyn Castle biomass. Hotting up and bye bye oil

I had a few minutes spare today and so popped over to have a look at how our new Penrhyn Castle biomass is progressing. The new building has a roof. Waiting for the PV system in a few weeks for … Continue reading

Posted in Biomass, Wales | Tagged , , , , , , , , , , | Leave a comment

Last major property in NT Wales getting off oil – Devil in the detail (again)

Penrhyn Castle biomass project is now into implementation and delivery, and as always devil is in the detail – in this case about 38 tonnes of detail with many wheels. Elgan the project manager’s first challenge was to ensure that … Continue reading

Posted in Biomass, Energy generation, uncategorized, Wales | Tagged , , , , , , , , , , , | 1 Comment

Location, location, location…..biomass and Penrhyn Castle

Elgan is Project Manager for the REI programme at Penrhyn Castle. For his sins he has to share an office with Keith and I (who as you know are never short of an opinion). Guest blog from Elgan on progress … Continue reading

Posted in Biomass, Energy generation, Regions, Wales | Tagged , , , , , , , , , , , | Leave a comment