The Anafon community hydro is now marching down the mountain

the snake factory is ready up on the mountain. the 10m sections of pipe are being welded together as we speak. Image Gavin Gatehouse

the snake factory is ready up on the mountain. the 10m sections of pipe are being welded together as we speak. Image Gavin Gatehouse

Its been a few months since I reported on the progress of the Anafon community hydro. The contractors are great, the weather has been superb and all is well with the world. Anafon hydro is a 270kw system and by hook and crook the community of Abergwyngregyn have made this project possible. But its great to see such rapid progress. Its fantastic working on this project with such a dedicated team. More please!

another day in the office. First 400m is now in

another day in the office. First 400m of pipe is now in @GavinGatehouse

the pipe route. PS the pipe has ready been installed and this is what it looks like after! Cool or what!

The pipe route. PS the pipe has ready been installed and this is what it looks like after! Cool or what! @GavinGatehouse

the business end is going in as we speak. the slab is now actually complete for the turbine building

The business end is going in as we speak. The slab is now actually complete for the turbine building @GavinGatehouse

This entry was posted in CommunityEnergy, Hydro, Wales and tagged , , , , , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s