Well Connected

Keith starting at the beginning of the piperun

Keith starting at the beginning of the piperun

We are on the home stretch with the heat pump installation at Plas Newydd. It has been 12 weeks since the heating was switched off and last week saw the final connection being made to link up the mansion.

Bracket added as we noticed movement once filled
Bracket added as we noticed movement once filled

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

We added a bracket to the foreshore pipes as slight movement was noticed following these being filled. Makes sense really as they settled. The bracket ensures no undue stress to connection points between pipes and pumphouse.

Louie explaining final connections

Louie explaining final connections

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The mains water supply has been split to feed the building, the pumphouse and the Stables – lots of new valves.Finally the pipes work their way down to the mansion where we see out with the old and in with the new.

Old and new heat main pipework side by side. Wonder why the old system was inefficient?

Old and new heat main pipework side by side. Wonder why the old system was inefficient?

This entry was posted in uncategorized and tagged , , , , , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s